C2AE February 10, 2025 Update
• Environmental Report in progress.• Coordination ongoing with NYS Agriculture & Markets.
• Preparing funding applications (USDA Rural Development and WIIA).
Projected Timeline
1. Questionnaire / Interest Survey (if necessary)2. Development of Potential Project Area
3. SEQR Process (2–3 months; targeted completion by January Board Meeting)
4. Preliminary Engineering Report & Environmental Report
5. USDA RD & EFC Funding Applications and environmental clearances (through Spring 2026)
6. Agency Comment Review & Response (anticipated early May 2026)
7. Funding Offer (anticipated late May 2026)
8. Final Map, Plan & Report (late May 2026)
9. Public Hearing & Resolution for Formation of District/Service Area (June 2026 Board Meeting)
10. Referendum (September 2026)
11. Application to Comptroller (if necessary)
12. Bond Resolution
13. Bond Anticipation Note
C2AE October 8, 2025 Review Meeting:
- Preliminary Engineering Report (PER) has been submitted; awaiting agency review
- Environmental Report still needed
- Application for WIIA submitted electronically on September 12, 2025
- Application for Congressional Funding submitted on April 28, 2025
C2AE July 3, 2025 Review Meeting:
- Prepare for bond resolution/public hearing process to enable WIIA application by September 12, 2025.
- Final Map, Plan, and Report (September 2025.
- Funding:
- DWSRT BIL-GS grant up to $5 million;
- DWSRT BIL-GS interest-free loan up to $14 million.
- We amended the Preliminary Engineering Report (PER) and have it submitted to the Department of Health.
- Lead Agency and SEQR letters have been sent out. We await responses from the various interested agencies and will update the Environment Report and complete Parts 2 and 3 of the Full Environmental Assessment Form (FEAF) in an effort to complete the SEQR process once responses are received.
- Congratulations! The Town was notified that as part of the 2024 Bipartisan Infracture Law General Supplemental funding through the Drinking Water State Revolving Fund (DWSRF) that this project is eligible for a grant award up to $5 million and interest-free financing of $14 million! We intend to also apply for USDA Rural Development funding through their RD Apply process, which will be ongoing while the required documentation is collected.
- Moving forward:
Questionnaire/Interest Survey (if necessary).Development of Potential Project Area.- SEQR Process (203 months working to complete by January Board Meeting).
Preliminary Engineering Reportand Environmemental Report (Amendment Nov. 8th).